The turnkey make-ready guide for manufactured housing communities

What belongs in a standard make-ready scope, what actually drives the day count, where turn times go wrong, and how to price turns so they compare across communities.

Make-ready is the line that repeats forever

Every vacancy in every community, indefinitely. That changes what matters about it.

The things that make a make-ready programme good are not craft. They are predictability, comparability and evidence — because a turn that is brilliant but unpredictable is worse for a lease-up plan than one that is adequate and reliable.

This guide is about getting those three.

The standard scope

A make-ready should be a written list. If it is a judgement call, it means something different in every community and every month, and none of your numbers compare.

Demolition and haul-offWhat is failing comes out. Debris leaves with the crew, never staged at the lot line.
SubfloorRepaired where sounding finds soft deck — priced by area actually replaced
FlooringFull replacement, community-standard spec
WallsVOG panel replacement or drywall repair, textured to match
PaintCommunity-standard colour and sheen throughout
Kitchen and bathRefresh per component against a written condition standard
Fixtures and hardwareReplaced, not cleaned. These are consumables on a turn.
ExteriorSkirting repair, entry door and lockset, steps and landing check
CleanDocumented, to a written standard

What is deliberately NOT in it: belly wrap, roof work, full deck replacement, leveling and anchoring, abatement, appliances. All of those are real work that some homes need — and pricing them inside a standard turn is exactly how a make-ready budget becomes a remodel budget without anyone deciding to spend the money.

Where turn times actually go

Not craft speed. Two things.

Undiscovered condition

A home whose floor system is failing throughout, or whose walls are past matching, is a remodel wearing a make-ready's clothes. Running it through the turn schedule produces a turn that takes three times as long and a unit that comes back.

The fix is a walk that assigns the right scope before the unit enters the schedule, not a crew discovering it on day two.

Long-lead items

A manufactured-home-sized tub. A cabinet run. A door that is not a stock width.

These are ordered at scope approval, not when the room is ready for them. That single change is usually the difference between a five-day turn and a fifteen-day one, and it costs nothing.

Variance beats the average

The number worth negotiating on a turn programme is not the mean day count. It is the spread.

A programme where every turn lands in a five-to-seven day window lets you build a lease-up plan. A programme averaging six days across a two-to-fifteen range does not, even though the average is identical — because you cannot commit a unit to a prospective tenant on an average.

Variance comes almost entirely from the two causes above. Address those and the spread collapses.

Pricing so the numbers compare

Per unit, by unit type and turn depth, as itemized line items.

  • Not hourly. Hourly gives you no basis for comparing communities and no alignment on speed.
  • Not one blended per-unit number. A blended figure hides which scope line drives a cost difference between two markets, and that is the line you need to act on.

An itemized quote is a small ask that changes what your data can tell you. Our published structure is at scopes and unit pricing.

Documentation at milestones

Photographs at defined points — pre-work, post-demolition, post-rough-in where applicable, and completion. Not a completion shot.

The value is not the record. It is that a regional manager who never visits the community can approve the work, which is the mechanism that lets an operator run communities they do not personally walk. It is also the difference between evidence and two recollections when a question comes up six months later.

A turn checklist worth stealing

  1. Walk before scheduling

    Assign the right scope. Flag the homes that are remodels. Look underneath — belly, piers, drainage.

  2. Order long-lead at approval

    Tubs, cabinets, non-stock doors. Not when the room is ready.

  3. Belly before floor

    Every time. Closing a belly after the floor is in means doing the floor twice.

  4. One spec per community

    One flooring product, one paint colour, one hardware finish. Future touch-ups become an hour instead of a day.

  5. Photograph at milestones

    Not at the end. The record is what makes remote approval possible.

  6. Close against a written punch

    Walked with the community manager. Disagreements happen while a crew is still on site.

Common questions

A written list rather than a judgement call. Ours covers demolition of what is failing, subfloor repair where needed, flooring, wall repair, paint, kitchen and bath refresh, fixtures and hardware, exterior and skirting, and a documented clean. Anything outside that list is a separate line, which is what keeps the standard turn comparable between communities.

The average matters less than the spread. A programme where every turn lands in a five to seven day window is far more useful to a lease-up plan than one averaging six days with a range of two to fifteen, because a plan is built on the window rather than the mean.

Two things, almost always. Undiscovered condition — a home that needed a remodel entering the turn schedule as a make-ready — and long-lead items ordered when the room was ready for them rather than at scope approval.

Per unit, as an itemized quote: every scope line priced on its own. Hourly pricing gives you no way to compare communities and no incentive alignment on speed. A single blended per-unit figure is better than hourly and still hides which part of the scope drives a cost difference.

Belly wrap. Nobody walks a unit and notices the belly, so it never appears on a walk sheet — and it is the reason a subfloor that was repaired last year is soft again.