Water, sewer, electrical and gas connected and inspected — the item that quietly controls the date a lot starts earning.

How it is priced
Per lot, by service and by what is found at the stub
Timeline
Set in your written estimate, after the walk-through
Who performs it
NRBS crews, self-performed

The scope that controls the calendar

Utility connection is a small amount of work and a large amount of elapsed time, and confusing the two is why infill programmes slip.

The physical connections are a matter of days. The queue — utility appointment, inspection, meter set — is weeks, and none of it is under a contractor's control. Where those queue items run in series rather than in parallel, and where nobody started them until the home was already on the lot, a two-week job becomes a two-month one.

This is the single most useful thing we do differently on an infill programme: utility scheduling starts at scope approval, not at delivery. It costs nothing to start early and it is often what decides when a lot starts earning.

What is at the stub is not knowable in advance

On a lot that has been vacant for years, the honest position is that nobody knows the condition of the existing services until they are exposed.

WaterCorroded stub, failed shut-off, or a line damaged when the previous home was removed
SewerDamaged connection, root intrusion, or a blockage that has been there since the last home left
ElectricalService sized for the previous home — often smaller than the one arriving
GasCapped stub of unknown condition; pressure testing is not optional

We price the connection work and carry the stub condition as a separate line, discovered and photographed rather than estimated. Padding every lot for a stub problem most lots do not have is how an infill budget stops being usable.

Electrical sizing, checked before the home is scheduled

A lot that previously held a small single-wide may carry a service that will not support a modern double-wide, particularly one with electric heat.

Discovering that at connection is a multi-week delay: an upgraded service is a utility company timeline, not a contractor timeline. We check the existing service against the incoming home during scoping, which is a fifteen-minute task that routinely saves a month.

Freeze protection and the skirt

In any community that sees hard freezes, exposed water runs under the home need heat tape and insulation, and they need it before the first cold night rather than after the first frozen line.

This connects directly to skirting: the skirt has to be closed for freeze protection to work, and ventilated correctly so that closing it does not create a moisture problem underneath. Those two requirements pull in opposite directions and both have to be satisfied. Doing one without the other is how a community trades frozen lines for rotted bellies.

Also in structural & site

Specification

What we install, and to what standard.

Full specification
Services
Water, sewer, electrical, and gas where the community is served
Freeze protection
Heat tape and insulation on exposed runs in northern communities
Inspection
Coordinated with the authority having jurisdiction before the skirt is closed
The unknown
The condition of the existing stub, which is not knowable until it is exposed

Not in the scope

  • Anything not written in the scope. Extra work found on site is raised as a written change order before it is done.

How the job runs

  1. Walk-through

    We walk the units or the roof, or work from the walk sheet you already have.

  2. Written scope

    A written scope and price before any work starts, priced as shown above.

  3. The work

    Our own crews do it, to the written scope. Anything extra is a written change order first.

  4. Final walk-through

    We walk it again with you and close out anything on the punch list.

Step one is your scope, as it already exists.

Request a bid

Pricing a whole community? Request a park-wide quote.

Common questions

Because the work is days and the scheduling is weeks. Connection itself is quick. Getting a utility appointment, getting an inspection, and getting a meter set are all queue times outside anyone's control, and they run in series unless someone starts them early. On most stalled infill programmes this is where the time went.

It is unknown until it is exposed, which is the honest answer. On a lot that has been vacant for years the water stub may be corroded, the sewer connection may be damaged or blocked, and the electrical service may be sized for a smaller home than the one arriving. None of that is visible from the surface.

Sometimes. A lot that previously held a small single-wide may have a service that will not carry a modern double-wide with electric heat. Finding that out at connection rather than at scoping is a multi-week delay, so we check the existing service against the incoming home before the home is scheduled.

In any community that sees hard freezes, exposed water runs under a home need heat tape and insulation, and the skirting has to be closed and ventilated correctly at the same time. A frozen supply line under an occupied home in January is the single most disruptive failure in this scope.

W-9, written safety programme and certificates of insurance (GL and workers’ comp): being prepared. What is published so far is on vendor credentials.